Question #: 22
Topic #: 3

An IT-related program has a critical team in a region experiencing a crisis. Due to uncertainty about the region's changing environment a company's senior leadership asks the program manager to decrease dependencies on the critical team that should the program manager do to mitigate the Impacts of this request?


A.

Update the procurement management plan, and begin the request for proposal (RFP) process to replace the critical team

by staff augmentation


B.

Meet with the steering committee to request assistance and influence in obtaining additional resources


C.

Level resources, and empower the critical team to complete its work before regional instability impacts its efforts


D.

Revisit the program management plan to clearly identify how decreasing critical team dependencies will impact component projects