Question #: 81
Topic #: 9

A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement

What should the program manager do first?


A.

Meet with the program management office to update the benefits management plan


B.

Meet with the organization's strategic planning committee to obtain clarification


C.

Meet with the program sponsor to address the issue


D.

Meet with the customer to determine if the stakeholder's requirement is valid