Questions # 21:

Which statement should be recorded under the Programme and Project Management heading?

Options:

A.

The Consortium has been formed to plan the transformation of education and learning for 11 to 18 year olds throughout the Western Area.


B.

The redefinition of jobs is to be negotiated with teaching unions and communicated to all staff.


C.

A financial special advisor has been appointed from Western Area Finance, an auditing organization.


D.

Plans could meet with substantial opposition from parents and staff.


Expert Solution
Questions # 22:

Answer the following questions about 'Ensuring Successful Delivery' for the Pittville project.

The best and final offers have been returned for the delivery of the new campus. The preferred supplier was a

construction enterprise called Piaffeco.

Column 1 contains activities taken in the Pittville project. For each entry in Column 1, select from Column 2 the Action within the

Five Case Model that should undertake this activity. Each selection from Column 2 can be used once, more than once or not at all.

Question # 22

Question # 22


Expert Solution
Questions # 23:

Answer the following question about the Economic Case within the Outline Business Case

(OBC).

The Preferred Way Forward is the Service Solution to provide a new Learning Campus on the

Old Fire Station Headquarters site and to close and transfer all further education units in the

Pittville area. However there are concerns that the project timescale may be difficult to keep

due to the following reasons:

. Planning authority consent may delay the schedule because the site is in a conservation

area

. Staff and students could be opposed to moving location.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each

line identify the appropriate option, from options A to E, that applies. Each option can be used once,

more than once or not at all.

Question # 23

Question # 23

Question # 23


Expert Solution
Questions # 24:

Which 2 statements should be recorded under the Proposed charging mechanisms heading?

Options:

A.

The cost of any changes to the contract will need to be authorized by the Programme Change Board.


B.

The new campus building is to be listed as an asset on the Local Education Authority balance sheet.


C.

The return on the investment will repay the sum of the original investment over 10 years.


D.

The contract period for development of the new campus is three years.


E.

20% of the contract price is to be paid up front for materials.


Expert Solution
Questions # 25:

The Central Government funding programme for the redevelopment of schools has been put on hold. A Review Board will decide

which programmes to continue. This funding programme covers 20% of the Pittville project costs. It is considered very likely that

the Western Area Learning Programme will be high priority due to the forecast enhanced provision of education courses for 16-18

year olds.

Should the funding profile in the Economic Case be updated?

Options:

A.

No, because the funding statement is provided in the Financial Case.


B.

No, because the Economic Case should have already quantified this funding risk.


C.

Yes, because alternative monies may be available to fund proposals that offer demonstrably better value for money.


D.

Yes, because scenario analysis should reflect the political uncertainties on which the success of the proposal depends.


Expert Solution
Questions # 26:

Answer the following question about the Outline Business Case.

The following questions include only true statements about the Pittville project.

However only one statement is an appropriate entry for that heading in the

Management Case section.

Which statement should be recorded under the Programme and Project Management heading?

Options:

A.

Projected inflation will mean that costs will be 6% higher when the campus is operational.


B.

Temporary accommodation will be put on the site of the Old Fire Station Headquarters at least 3 months before the development of the new campus takes place.


C.

Opportunities will be created for teachers to be involved in delivering new courses.


D.

The chosen service provider must have experience in the construction of publicly used buildings.


Expert Solution
Questions # 27:

Which 2 details should be defined when determining spending objectives?

Options:

A.

Targeted outcomes and 'where we want to be'.


B.

The problems, difficulties and inadequacies associated with 'where we are now'.


C.

The boundaries, or limitations, of the project.


D.

How services are currently organized, provided and supplied.


E.

Public value in terms of return for money spent.


Expert Solution
Questions # 28:

Which 2 attributes demonstrate that this option supports the key CSF Potential value for money?

Options:

A.

New opportunities will be available for teachers to be involved in delivering the new education courses.


B.

The 'BAU/status quo' option is the baseline for assessing value for money.


C.

There is a reasonably positive reaction from local schools to the Old Fire Station Headquarters being used as a second site.


D.

The demographic forecasts are for further reductions in the demand for places over the next five years.


E.

A new campus would provide modern and better facilities at a cheaper cost than refitting existing buildings.