APMG-International Better Business Cases Practitioner Exam Better-Business-Cases-Practitioner Question # 23 Topic 3 Discussion

APMG-International Better Business Cases Practitioner Exam Better-Business-Cases-Practitioner Question # 23 Topic 3 Discussion

Better-Business-Cases-Practitioner Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

Answer the following question about the Economic Case within the Outline Business Case

(OBC).

The Preferred Way Forward is the Service Solution to provide a new Learning Campus on the

Old Fire Station Headquarters site and to close and transfer all further education units in the

Pittville area. However there are concerns that the project timescale may be difficult to keep

due to the following reasons:

. Planning authority consent may delay the schedule because the site is in a conservation

area

. Staff and students could be opposed to moving location.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each

line identify the appropriate option, from options A to E, that applies. Each option can be used once,

more than once or not at all.

Better-Business-Cases-Practitioner Question 23

Better-Business-Cases-Practitioner Question 23

Better-Business-Cases-Practitioner Question 23