APMG-International Better Business Cases Practitioner Exam Better-Business-Cases-Practitioner Question # 24 Topic 3 Discussion

APMG-International Better Business Cases Practitioner Exam Better-Business-Cases-Practitioner Question # 24 Topic 3 Discussion

Better-Business-Cases-Practitioner Exam Topic 3 Question 24 Discussion:
Question #: 24
Topic #: 3

Which 2 statements should be recorded under the Proposed charging mechanisms heading?


A.

The cost of any changes to the contract will need to be authorized by the Programme Change Board.


B.

The new campus building is to be listed as an asset on the Local Education Authority balance sheet.


C.

The return on the investment will repay the sum of the original investment over 10 years.


D.

The contract period for development of the new campus is three years.


E.

20% of the contract price is to be paid up front for materials.


Get Premium Better-Business-Cases-Practitioner Questions

Contribute your Thoughts:


Chosen Answer: