APMG-International Better Business Cases Practitioner Exam Better-Business-Cases-Practitioner Question # 25 Topic 3 Discussion

APMG-International Better Business Cases Practitioner Exam Better-Business-Cases-Practitioner Question # 25 Topic 3 Discussion

Better-Business-Cases-Practitioner Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

The Central Government funding programme for the redevelopment of schools has been put on hold. A Review Board will decide

which programmes to continue. This funding programme covers 20% of the Pittville project costs. It is considered very likely that

the Western Area Learning Programme will be high priority due to the forecast enhanced provision of education courses for 16-18

year olds.

Should the funding profile in the Economic Case be updated?


A.

No, because the funding statement is provided in the Financial Case.


B.

No, because the Economic Case should have already quantified this funding risk.


C.

Yes, because alternative monies may be available to fund proposals that offer demonstrably better value for money.


D.

Yes, because scenario analysis should reflect the political uncertainties on which the success of the proposal depends.