Questions # 21:

Which 2 statements explain why the Contract Architect would be an appropriate Technical Co-ordinator?

Options:

A.

Is an external consultant.


B.

Has good leadership skills.


C.

Has experience of working with the company previously.


D.

Has a good, technical understanding of the work of the other professionals engaged in the project.


E.

Is an authority on local planning applications.


Expert Solution
Questions # 22:

How should the Project Manager assist the electricians to deliver the wiring?

Options:

A.

Provide separate electricians' rooms so they can focus on their work.


B.

Hold a weekly meeting for electricians so they can report on progress.


C.

Encourage the Business Ambassador to be available to discuss location of electrical sockets.


D.

Produce a detailed design of all electrical socket locations, to be approved by the Technical Co-ordinator.


Expert Solution
Questions # 23:

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because only Must Have requirements should be fully understood.


B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.


C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.


D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.


Expert Solution
Questions # 24:

The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in

the gardens could be enjoyed.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.


B.

Deliver on time.


C.

Collaborate.


D.

Never compromise quality.


Expert Solution
Questions # 25:

Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?

Options:

A.

Accustomed to bringing in contract staff for short periods of time.


B.

Closely manages the building team so that they consistently produce high-quality work.


C.

Is able to represent the team in all daily meetings.


D.

An experienced builder who is good at turning a brief into a practical design.


E.

Is empowered by Timber Tigers' management to make decisions on the building work.


Expert Solution
Questions # 26:

What action should the Project Manager take during the Close-Out of Timebox C?

Options:

A.

Remove 'Aspects' from the supplier list for all future projects.


B.

Carry out final checks to ensure the deliverables of Timebox C meet the expected standards.


C.

Ensure that lessons are learned so that similar issues do not occur in future Timeboxes.


D.

Initiate the work required to complete the windows to the required standard.


Expert Solution
Questions # 27:

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

At the beginning of Solution Development Timebox A, the Timebox is being

planned in detail. Although Foundations was conducted at a high level, the

Prioritised Requirements List was baselined. Now the Solution Development

Team is setting detailed acceptance criteria against each requirement.

Is this an appropriate approach to setting detailed acceptance criteria?

Options:

A.

Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.


B.

Yes, because the Solution Development Team members will be setting acceptance criteria for the first time during Solution Development Timebox A.


C.

No, because the Solution Development Team should NOT be involved in setting acceptance criteria.


D.

No, because acceptance criteria should be set in detail against each requirement during Foundations.


Expert Solution
Questions # 28:

The Close Out of Timebox B was completed as scheduled, but the Could Have requirement of tiled walls in the bathrooms was NOT delivered within this period, with the

agreement of the team.

Which Agile principle MOST influences this course of action?

Options:

A.

Deliver on time.


B.

Never compromise quality.


C.

Build incrementally from firm foundations.


D.

Develop iteratively.


Expert Solution
Questions # 29:

Xan Insurance Company operates from one location - a large, open-plan

office in the centre of a city. Those employees that will be working within the

Solution Development Team are all based in this office but work at different

ends of the office in separate departments.

What action should the Project Manager suggest to ensure the most effective

collaboration of the Solution Development Team?

Options:

A.

Create an email group for the Solution Development Team to collaborate

on ideas.


B.

Set up a telephone or video conferencing facility so that all members of

the team can collaborate effectively.


C.

Relocate these employees to a new project area, with a number of desks

where the Solution Development Team can sit together.


D.

No action required as these employees are located in the same office.


Expert Solution
Questions # 30:

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.


B.

The Project Manager should do nothing during a Timebox.


C.

Attend the Daily Stand-up and discuss any problems at the end.


D.

Update the Team Board with a summary of team progress and the current

status of work.


Expert Solution