AgilePM-Practitioner Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.

Is this an appropriate action related to acceptance criteria?


A.

Yes, because only Must Have requirements should be fully understood.


B.

Yes, because the acceptance criteria might need to be changed during the Solution Development Timebox.


C.

No, because it is necessary to understand the full detail of all the work for completion in the Solution Development Timebox during Investigation.


D.

No, because it indicates that the Solution Development Team has NO intention of delivering the Should Have requirements.