The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Maintain a tight control on progress, recording all discussions and making
all decisions.
The Project Manager should do nothing during a Timebox.
Attend the Daily Stand-up and discuss any problems at the end.
Update the Team Board with a summary of team progress and the current
status of work.
Submit