APMG-International Agile Project Management (AgilePM) Practitioner Exam AgilePM-Practitioner Question # 30 Topic 4 Discussion

APMG-International Agile Project Management (AgilePM) Practitioner Exam AgilePM-Practitioner Question # 30 Topic 4 Discussion

AgilePM-Practitioner Exam Topic 4 Question 30 Discussion:
Question #: 30
Topic #: 4

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?


A.

Maintain a tight control on progress, recording all discussions and making

all decisions.


B.

The Project Manager should do nothing during a Timebox.


C.

Attend the Daily Stand-up and discuss any problems at the end.


D.

Update the Team Board with a summary of team progress and the current

status of work.