APMG-International Agile Project Management (AgilePM) Practitioner Exam AgilePM-Practitioner Question # 26 Topic 3 Discussion

APMG-International Agile Project Management (AgilePM) Practitioner Exam AgilePM-Practitioner Question # 26 Topic 3 Discussion

AgilePM-Practitioner Exam Topic 3 Question 26 Discussion:
Question #: 26
Topic #: 3

What action should the Project Manager take during the Close-Out of Timebox C?


A.

Remove 'Aspects' from the supplier list for all future projects.


B.

Carry out final checks to ensure the deliverables of Timebox C meet the expected standards.


C.

Ensure that lessons are learned so that similar issues do not occur in future Timeboxes.


D.

Initiate the work required to complete the windows to the required standard.


Get Premium AgilePM-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.