The Change Manager is looking to develop the change agent network that will support the changes related to the Operational delivery processes workstream.
Which information is MOST likely to be relevant for the change agents when being inducted into the change programme for the Operational delivery processes workstream?
The Change Manager has read Goleman's articles on the Hay-McBer six dimension model of organization climate. This gives leaders practical ways that
leadership style can improve organizational culture and performance as measured by staff surveys.
Answer the following question about recommendations a change manager could make to the CEO applying these six dimensions to improve climate across the
organization.
Column 1 is a list of recommendations the Change Manager has made to the CEO seeking to initiate or support a change in the organizational culture. For each
recommendation in Column 1, select from Column 2 the 'dimension' in organizational climate MOST likely to improve as a result. Each selection from Column 2 can be
used once, more than once or not at all.
Which is the BEST reason to remind learners of related knowledge or skill they already possess?
Sales staff are unhappy that they have been told that they will lose the Sales relaxation area completely to make space for the new Selco staff. The Sales staff are considering consulting their Union about escalating their discontent.
Which 2 actions by the Sales Director are the MOST appropriate when responding to this type of resistance?
The Timebox to deliver the online reservation system through the Hoy Hall website has experienced a major issue. During Timebox C a test was completed to
simulate an attack on the financial element of the online reservation system, with the intention of finding security weaknesses. It was found that it was
potentially possible to gain access to the system, its functionality and data. Further work is therefore needed to meet the information security elements of a
customer financial transaction.
Answer the following question about the actions to be taken by each role.
Column 1 describes a list of actions related to dealing with the security issue with the hotel reservation system. Column 2 lists the key roles. For each action in Column 1,
select from Column 2 the role that should carry out the action.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1
Advise how the legislation on the transfer of data will affect the requirements
and the system.
Agree the changes needed to the corporate technical architecture with the
Architecture Angels IT support team.
Ensure the information security vulnerability is communicated to the AA Head
Office IT Director.
Evaluate the impact of proposed security controls on the business and decide
on the most suitable solution.
Reprioritise the requirements on the Prioritised Requirements List associated
with the security issue.
Column 2
Project Manager
Business Sponsor
Business Visionary
Technical Coordinator
Business Analyst
Team Leader
Business Ambassador
Solution Developer
During Timebox B, the 'Hoy for Hoy Hall'Action Group disagreed about the planned outcome of the Timebox. The Project Manager organised a Facilitated Workshop to re-
engage this group and explore discrepancies in understanding.
Is this an appropriate application of Agile Project Management for this project?
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
What action should the Project Manager take to plan the deployment activities?
The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are
four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and
to know who should be where. Some of the contractors have started to turn up late to the site.
Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The
Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.
Answer the following questions about motivating the contractor teams according to Agile Project Management.
How should the Project Manager encourage the resources to operate more successfully?
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The objective of Solution Development Timebox B is to ensure that the front and east wings are finished and approved. The Project Manager has pointed out that acceptance criteria for this part of the solution need to be agreed.
Is this an appropriate action related to acceptance criteria?