AgilePM-Practitioner Exam Topic 3 Question 20 Discussion:
Question #: 20
Topic #: 3

Time is running short and the Must Have requirements for the data entry screen

of the web page, as recorded in the Prioritised Requirements List, are not going

to be completed on time.

What action should the Project Manager take?


A.

Change the end date of the Timebox.


B.

Ensure that this issue is escalated to the project level roles.


C.

Amend the end date in the Delivery Plan.


D.

Accept that the Must Have requirements will not be delivered on time.