Question #: 18
Topic #: 2

What action should the Project Manager take to plan the deployment activities?


A.

Prepare a Timebox Plan for the next Development Timebox.


B.

Check the Delivery Plan for deployment activities and update as required.


C.

Create a plan of activities to deploy the solution at the end of Timebox C.


D.

Update the Timebox Plan for Timebox C with the activities required to deploy the solution.