Question #: 18
Topic #: 2

Which 2 statements represent appropriate entries for the Development

Approach Definition?


A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.


B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.


C.

An easy to use web development tool called ' WebMatrix ' is to be used to

develop and maintain the website extension.


D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.


E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.