Viewing page 3 out of 6 pages
Viewing questions 21-30 out of questions
Questions # 21:

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.


B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.


C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.


D.

Source and hire a web developer with experience in developing online

financial transaction functionality.


E.

Consolidate and circulate an agenda for the workshop.


Expert Solution
Questions # 22:

How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

Options:

A.

The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.


B.

The Solution Development Team should commence understanding and delivering the new requirement.


C.

The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels ' Senior Management Team.


D.

The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.


Expert Solution
Questions # 23:

Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.

Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.

Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully

meet Hoy Hall requirements, after deployment.

2. Developing a fully functioning in-house system, developed and hosted by Architecture

Angels IT Operations team.

3. All-in-one web-based reservation and accommodation management system built to Hoy Hall ' s

specification.

4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group,

until a suitable system can be implemented at the site.

5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.

Column 2

    Maintainability is a required attribute of the initial delivered solution

    Deliver first, re-engineer later

    Short-term, tactical solution

Question # 23


Expert Solution
Questions # 24:

The building has had all the old utility services removed and new wiring and plumbing is being installed during Evolutionary Development. On average there are

four electrical and six plumbing contractors who are engaged for between a few days and a few weeks. They are finding it difficult to work round each other and

to know who should be where. Some of the contractors have started to turn up late to the site.

Many floor boards have been lifted in preparation but it is not clear where the radiators are being situated or when each room is going to be worked on by the plumbers. The

Chief Accountant, acting as Business Ambassador, is also alarmed that the electrical sockets are being installed in rooms in inaccessible locations.

Answer the following questions about motivating the contractor teams according to Agile Project Management.

How should the Project Manager encourage the resources to operate more successfully?

Options:

A.

Facilitate a workshop with the Solution Development Team to establish a co-ordinated Timebox Plan.


B.

Hold a separate Daily Stand-up meeting for contractors only.


C.

Provide a detailed plan of activity for each contractor team.


D.

Schedule the electrical and plumbing teams so that they work on different Timeboxes.


Expert Solution
Questions # 25:

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

Options:

A.

Marketing Director, in the role of Business Visionary.


B.

Team Leader.


C.

Project Manager and Architect, in the role of Technical Co-ordinator.


D.

Architecture Angels ' Senior Management Team.


Expert Solution
Questions # 26:

During Refinement in Timebox B, a Review Session was scheduled for the Business Visionary to review the products completed during this Timebox, and to agree what

needed to be done before these would be acceptable.

Is this an appropriate application of Agile Project Management for this project?

Options:

A.

Yes, because this will enable the Solution Development Team to ensure they are on track to deliver a viable solution.


B.

Yes, because this allows each team member working in the Timebox to provide a short progress report and raise any issues that hinder their progress.


C.

No, because early and frequent visibility of the product features will maintain engagement with the stakeholders.


D.

No, because only members of the Solution Development Team are permitted to attend Review Sessions.


Expert Solution
Questions # 27:

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

At the beginning of Solution Development Timebox A, the Timebox is being

planned in detail. Although Foundations was conducted at a high level, the

Prioritised Requirements List was baselined. Now the Solution Development

Team is setting detailed acceptance criteria against each requirement.

Is this an appropriate approach to setting detailed acceptance criteria?

Options:

A.

Yes, because acceptance criteria can only be understood at a high level during Foundations and will always need further investigation.


B.

Yes, because the Solution Development Team members will be setting acceptance criteria for the first time during Solution Development Timebox A.


C.

No, because the Solution Development Team should NOT be involved in setting acceptance criteria.


D.

No, because acceptance criteria should be set in detail against each requirement during Foundations.


Expert Solution
Questions # 28:

Find out who is responsible for challenging the priority of requirements and deal with them accordingly.

Options:

A.

Ask the Team Leader to resolve the situation.


B.

Ask the Marketing Director to explain to the Solution Development Team why the windows are a Must Have priority.


C.

Remove empowerment from the Solution Development Team.


D.

What action should the Project Manager take when dealing with the Solution Development Team ' s argument that the windows should not be a Must Have priority?


Expert Solution
Questions # 29:

Using the additional information provided for this question in the Scenario Booklet, answer the following questions about the requirement for a fire exit from the

upstairs of the building.

What is an appropriate reason to classify the need for a secondary exit from the upstairs of the building as a Must Have requirement?

Options:

A.

Provision of a secondary exit from the upstairs of the building will ensure compliance with national fire safety regulations.


B.

A secondary exit from the upstairs of the building would help ease congestion in busy periods during festivals.


C.

A secondary exit from the upstairs of the building will provide a shorter and more direct route into the garden than the main stairway.


D.

The requirement for a secondary exit from the upstairs of the building has to be made a higher priority in order to be moved to an earlier Timebox.


Expert Solution
Questions # 30:

The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open

Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.

At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.

However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video

tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of

storage space on the company server and require minimal maintenance.

The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.

Remember to limit your answers to the number of selections requested in each question.

Which 2 individuals should the Facilitator invite to participate in the Workshop?

Options:

A.

Chief Executive (Steering Group)


B.

Representative for Earth Excavations (Solution Developer)


C.

Representative for Timber Tigers (Solution Developer)


D.

IT Operations Manager (Solution Development Team)


E.

Marketing Director (Business Visionary)


Expert Solution
Viewing page 3 out of 6 pages
Viewing questions 21-30 out of questions