Questions # 1:

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

Question # 1

The equivalent value of an investment alternative in today's dollars is referred to as the:

Options:

A.

Break-even point


B.

Rate of return


C.

Net present worm


D.

Future value


Expert Solution
Questions # 2:

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the company needs to repay a loan of $100,000 in 10 uniform annual payments, how much will each payment be?

Options:

A.

$16,380


B.

$16,578


C.

$15,937


D.

$16,273


Expert Solution
Questions # 3:

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

Question # 3

The longest path depends upon relationships driving the timing of activity starts, therefore the following scheduling features should not be used in calculating file longest path.

Options:

A.

milestone activities


B.

activities with lag


C.

activities with short durations


D.

constraints, resource leveling, and interruptible activities


Expert Solution
Questions # 4:

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What information is needed to develop a Class 2 definitive estimate?

Options:

A.

Soil data, detailed construction drawings, quantity takeoffs, minimum contingency detailed indirect costs, detailed engineering estimates


B.

Preliminary quantities with labor, material, and factors applied, square footage of facilities, minimum contingency detailed indirect costs


C.

Square footage of facilities, factored indirects and home office costs


D.

Vendor quotes, home office detailed estimate, preliminary quantities with labor, material, and factors applied


Expert Solution
Questions # 5:

Which of the lol owing comparisons is commonly used in forensics schedule analysis (FSA)?

Options:

A.

Cost performance index (CPI) to schedule performance index (SPI)


B.

Forensic productivity analysis


C.

Earned value vs scheduled value


D.

As-planned vs as-built


Expert Solution
Questions # 6:

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following is considered a measure of profitability?

Options:

A.

Rate of return


B.

Annual Dividends


C.

Total assets


D.

Annual sales


Expert Solution
Questions # 7:

Question # 7

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Given a unit price contract between the owner and contractor, each assumes the following:

Options:

A.

Bid unit rate, owner quantities can exceed estimate range Contractor can perform above


B.

Bid unit rate, owner quantities are within estimate range


C.

Contractor can perform at or below bid unit rate, owner quantities can exceed estimate range


D.

Contractor can perform at or below bid unit rate, owner quantities are within estimate range


Expert Solution
Questions # 8:

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?

Options:

A.

Recalculate the early finish for each activity


B.

Recalculate the early start for each activity


C.

Update the remaining duration for each activity


D.

Recalculate the critical path


Expert Solution
Questions # 9:

Question # 9

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

Options:

A.

8.7%


B.

8.2%


C.

4.6%


D.

8.0%


Expert Solution
Questions # 10:

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Which of the following statements is the more correct guide for the Project Cost engineer as the compiles the data information?

Options:

A.

Only quantitative data can have means, medians and modes, as these require number rankings.


B.

There is no difference between quantitative data, qualitative data and histogram data except in the manner in which it is presented.


C.

Some graphic methods tor describing qualitative data are range variance and


Expert Solution