Question #: 3
Topic #: 1

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

CCP Question 3

The longest path depends upon relationships driving the timing of activity starts, therefore the following scheduling features should not be used in calculating file longest path.


A.

milestone activities


B.

activities with lag


C.

activities with short durations


D.

constraints, resource leveling, and interruptible activities