A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What information is needed to develop a Class 2 definitive estimate?


A.

Soil data, detailed construction drawings, quantity takeoffs, minimum contingency detailed indirect costs, detailed engineering estimates


B.

Preliminary quantities with labor, material, and factors applied, square footage of facilities, minimum contingency detailed indirect costs


C.

Square footage of facilities, factored indirects and home office costs


D.

Vendor quotes, home office detailed estimate, preliminary quantities with labor, material, and factors applied