AACE International Certified Cost Professional (CCP) Exam CCP Question # 8 Topic 1 Discussion

AACE International Certified Cost Professional (CCP) Exam CCP Question # 8 Topic 1 Discussion

CCP Exam Topic 1 Question 8 Discussion:
Question #: 8
Topic #: 1

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The project scheduler left the company and has left unfinished work. You have been hired as the new project scheduler and must update the existing schedule. What will be your first task?


A.

Recalculate the early finish for each activity


B.

Recalculate the early start for each activity


C.

Update the remaining duration for each activity


D.

Recalculate the critical path


Get Premium CCP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.