Questions # 21:

Why should the Product Owner care that the Developers adhere to the Definition of Done?

(choose the best two answers)

Options:

A.

To influence the Total Cost of Ownership of the product.


B.

To have transparency into what has been done at the end of each Sprint.


C.

To be able to reprimand the team when they do not meet their velocity goal forthe Sprint.


D.

To ensure the Developers achieve a high level of productivity over time.


Expert Solution
Questions # 22:

What activities would a Product Owner typically undertake in the phase between the end of the

current Sprint and the next Sprint ' s Sprint Planning?

(choose the best answer)

Options:

A.

Working with the Quality Assurance departments on the Increment of the currentSprint.


B.

There are no such activities. The next Sprint starts immediately after the currentSprint.


C.

Updating the project plan with the stakeholders.


D.

Refining the Product Backlog.


Expert Solution
Questions # 23:

Which of the following might be considered when ordering Product Backlog items?

(choose all that apply)

Options:

A.

Dependencies to other products.


B.

Value of Product Backlog items.


C.

Dependencies between Product Backlog items.


D.

Cost of delay.


E.

Cost of implementation.


Expert Solution
Questions # 24:

Which activities will a Product Owner likely engage in during a Sprint?

(choose the best three answers)

Options:

A.

Reorder items in the Product Backlog.


B.

Answer questions from the Developers about items in the current Sprint.


C.

Update the Sprint burndown chart.


D.

Prioritize the Developer ' s tasks.


E.

Gather information and opinions from stakeholders.


F.

Run the Daily Scrum.


Expert Solution
Questions # 25:

You are a Product Owner for a product with a rapidly declining customer base.

Despite data that indicates the decline is due to a shrinking market, rather than a lack of new

features, an influential stakeholder insists on adding more features to attract new customers.

The influential stakeholder also says that if you do not add new features you risk losing your

most profitable customer.

Which two of the following actions might you take?

(choose the best two answers)

Options:

A.

Collaborate with the stakeholder to run a small experiment to validate theiropinion.


B.

Collaborate with other stakeholders and use a voting system to decide whichoptions should be considered.


C.

Acknowledge the views of the influential stakeholder but decline to add morefeatures to the product.


D.

Agree with the stakeholder and add features to the Product Backlog as it mightincrease your customer base.


Expert Solution
Questions # 26:

What is the Product Owner responsible for during the Sprint Retrospective?

(choose the best answer)

Options:

A.

Capturing requirements for the Product Backlog.


B.

They do not have to be there.


C.

Participating as a Scrum Team member.


D.

Summarizing and reporting the discussions to the stakeholders that they represent in the Scrum Team.


Expert Solution
Questions # 27:

Choose the two measurements which provide the best indicator to the Product Owner that

value is being delivered.

(choose the best two answers)

Options:

A.

Customer satisfaction.


B.

On-time release trends.


C.

Velocity.


D.

Frequency of feature use.


E.

Scope implemented.


Expert Solution