Questions # 1:

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (Choose two.)

Options:

A.

A shared understanding of the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal.


B.

An update of completed tasks and of the remaining work so the Scrum Master can plan the next day.


C.

A status report for the upper management indicating what each individual has done, will be doing, and what is impending him/her.


D.

An updated Scrum board to make Sprint progress transparent for the stakeholders.


E.

New impediments for the Scrum Master to take care of.


Expert Solution
Questions # 2:

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)

Options:

A.

There should be six Product Owners, one tor each Scrum Team.


B.

There should be six Product Owners, reporting to a Chief Product Owner.


C.

The product has one Product Backlog.


D.

Each Scrum Team should have a separate Product Backlog.


E.

There should be only one Product Owner.


Expert Solution
Questions # 3:

Multiple Scrum Teams working on the same project must have the same Sprint start date.

Options:

A.

True


B.

False


Expert Solution
Questions # 4:

Cross-functional teams are optimized to work on one technical layer of a system only (e.g. GUI, database, middle tier, interfaces).

Options:

A.

True


B.

False


Expert Solution
Questions # 5:

During a Sprint Retrospective, the Development Team proposes moving the Daily Scrum to only occur on Tuesdays and Thursdays. Which two are the most appropriate responses for the Scrum Master? (Choose two.)

Options:

A.

Consider the request and decide on which days the Daily Scrum should occur.


B.

Coach the team on why the Daily Scrum is important as an opportunity to update the plan.


C.

Have the developers vote.


D.

Learn why the Development Team wants this and work with them to improve the outcome of the Daily Scrum.


E.

Acknowledge and support the self-organizing team’s decision.


Expert Solution
Questions # 6:

True or False A scrum Master fulfills the same role as a traditional Project Manager

Options:

A.

True


B.

False


Expert Solution
Questions # 7:

What is the timebox for the sprint Review? (choose the best answer)

Options:

A.

1 day


B.

4 hours for a one-month Sprint.


C.

As long as needed


D.

2 hours for a one-month Sprint.


Expert Solution
Questions # 8:

Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?

Options:

A.

Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint.


B.

Teach them that it is their responsibility to work with the other teams to create an integrated Increment.


C.

Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.


D.

Visit the five teams each day to inspect that their Sprint Backlogs are aligned.


Expert Solution
Questions # 9:

Which of the following might the Scrum Team discuss during a Sprint Retrospective?

Options:

A.

Methods of communication.


B.

The way the Scrum Team does Sprint Planning.


C.

Skills needed to improve the Development Team’s ability to deliver.


D.

Its Definition of “Done”.


E.

All of the above.


Expert Solution
Questions # 10:

Select two ways in which technical debt impacts transparency. (Choose two.)

Options:

A.

When calculated and estimated, the total amount of technical debt shows exactly how long until the Product Owner can release the Increment.


B.

It leads to false assumptions about the current state of the system, specifically of an Increment being releasable at the end of a Sprint.


C.

As development progresses and code is added, the system becomes more difficult to stabilize, which results in future work being slowed down in unpredictable ways.


D.

It enhances transparency for the Product Owner as a Development Team is not allowed to do additional feature development in a Sprint as long as there is technical debt.


Expert Solution