The correct answer is B, because multiple Scrum Teams working on the same project do not have to have the same Sprint start date. The Scrum Guide states that “multiple Scrum Teams often work together on the same product. One product goal unites them. Therefore, they must mutually define and comply with a definition of ‘Done’ that applies to their combined work product.” Therefore, the synchronization of multiple Scrum Teams is based on their shared product goal and definition of ‘Done’, not on their Sprint start date.