Scrum Professional Scrum Master I PSM-I Question # 2 Topic 1 Discussion

Scrum Professional Scrum Master I PSM-I Question # 2 Topic 1 Discussion

PSM-I Exam Topic 1 Question 2 Discussion:
Question #: 2
Topic #: 1

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)


A.

There should be six Product Owners, one tor each Scrum Team.


B.

There should be six Product Owners, reporting to a Chief Product Owner.


C.

The product has one Product Backlog.


D.

Each Scrum Team should have a separate Product Backlog.


E.

There should be only one Product Owner.


Get Premium PSM-I Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.