The correct answers are C and E, because these statements explain what “Done” means. No work left from the definition of “Done” means that all Product Backlog items selected for a Sprint meet the quality criteria agreed upon by the Scrum Team. All work to create software that is ready to be released to end users means that the Increment is potentially releasable at any time during the Sprint.