Pass the NCARB Architect Registration Examination PDD Questions and answers with CertsForce

Viewing page 3 out of 3 pages
Viewing questions 21-30 out of questions
Questions # 21:

Which of the following documents defines the responsibilities and duties of the contractor during construction?

Options:

A.

A101


B.

A201


C.

B101


D.

G702


Expert Solution
Questions # 22:

Question # 22

Refer to the exhibit.

An architect is working on an airport lounge project. The 9,000 SF floor plan includes an open, double-height space. Due to area limitations, all program requirements cannot fit within the 9,000 SF floor plan. A mezzanine level with one exit is being proposed to solve this programming constraint. There are adequate exits available on the main floor plan to pick up the additional occupant load from the mezzanine.

Which method of mezzanine construction should the architect design?

Options:

A.

2,500 SF open lounge area for 20 people


B.

2,750 SF enclosed business center for 15 people


C.

3,250 SF open dining area for 30 people


Expert Solution
Questions # 23:

Option 1 is the originally designed connection detail for a banner hanging system of steel tube beams and threaded rods in a high atrium space. The threaded rod connections to the structure are fabricated as part of the structure. The remaining members are field fabricated. The weights of beam and banner are identical at each level. Option 2 has been proposed to alleviate constructability issues. The structural ramifications must be evaluated before this change can be approved.

Click on the nut in option 2 that will realize a greater load due to the proposed change.

Question # 23


Expert Solution
Questions # 24:

During drawing review, a discrepancy is found between the drawings and room 101 on the finish schedule.

Click in the cell on the room finish schedule that does not match the drawings.

Question # 24


Expert Solution
Questions # 25:

For which of the following reasons is sheet piling used? (Check the three that apply)

Options:

A.

A grade beam needs support.


B.

Raked shoring should be created.


C.

A pile cap needs support.


D.

An excessive slope on the sides of the excavation would be required.


E.

The soil surrounding an excavation site will not support itself during or after the digging.


F.

The excavation adjoins a property line and the adjacent property cannot be disturbed.


Expert Solution
Questions # 26:

Question # 26

Refer to the exhibit.

The metal connector shown is primarily designed to resist which one of the following?

Options:

A.

Sliding


B.

Racking


C.

Uplift


D.

Twisting


Expert Solution
Questions # 27:

Why is the vertical surface of a dry-stacked stone wall often battered into the retained material?

Options:

A.

Increased resistance to soil thrust


B.

Increased resistance to surface erosion of the wall


C.

Increased impermeability that reduces equivalent fluid pressure


D.

Increased cohesion between individual stones that make up the wall


Expert Solution
Questions # 28:

Question # 28

Refer to the exhibit.

Which device allows for piping misalignment and isolation?

Options:

A.

A


B.

B


C.

C


D.

D


Expert Solution
Questions # 29:

The architect has completed 60% of the construction documents. The owner wants to establish the guaranteed maximum price (GMP) at this point before 100% of the construction documents are complete. Several flooring finish items are still undetermined.

What should be included in the project manual to make sure the contractor has a cost to cover all finishes?

Options:

A.

Contingency of 10% added to the overall construction cost


B.

Schedule of flooring unit prices to be completed by the contractor


C.

Allowance of $30/sq. yd. for floor finishes


D.

Alternate to change broadloom carpet to carpet tile


Expert Solution
Questions # 30:

Which of the following best explains the function of Division 01 in the specifications?

Options:

A.

Describes specific materials and installation


B.

Details bidding and contract forms


C.

Establishes general administrative requirements


D.

Identifies drawing scales and symbols


Expert Solution
Viewing page 3 out of 3 pages
Viewing questions 21-30 out of questions