NCARB ARE 5.0 Project Development and Documentation Exam PDD Question # 29 Topic 3 Discussion

NCARB ARE 5.0 Project Development and Documentation Exam PDD Question # 29 Topic 3 Discussion

PDD Exam Topic 3 Question 29 Discussion:
Question #: 29
Topic #: 3

The architect has completed 60% of the construction documents. The owner wants to establish the guaranteed maximum price (GMP) at this point before 100% of the construction documents are complete. Several flooring finish items are still undetermined.

What should be included in the project manual to make sure the contractor has a cost to cover all finishes?


A.

Contingency of 10% added to the overall construction cost


B.

Schedule of flooring unit prices to be completed by the contractor


C.

Allowance of $30/sq. yd. for floor finishes


D.

Alternate to change broadloom carpet to carpet tile