Pass the NCARB Architect Registration Examination PDD Questions and answers with CertsForce

Viewing page 1 out of 3 pages
Viewing questions 1-10 out of questions
Questions # 1:

During CD phase, the architect notices plumbing lines clash with roof trusses. What should the architect do first?

Options:

A.

Revise the truss design


B.

Notify the contractor


C.

Consult with the plumbing engineer


D.

Add soffits to conceal pipes


Expert Solution
Questions # 2:

A family-owned apple farm in the Upper Midwest is taking advantage of a change in the local zoning code that added a new Agri-Tourism class in the existing farm zone. This allows the Owner to build a new facility on their existing site. The building will be open to the public and include a brewery, distillery, tap room, and market. The architect is ready to submit the drawings to the Owner for the 50% construction documents review.

To accommodate a compressed construction schedule, the Owner will be utilizing a design-build process. The Contractor has submitted the Pre-Engineered Metal Building (PEMB) shop drawings to the Architect for review, due to the lead time on this critical path item. Once construction begins, farming operations must be able to continue uninterrupted.

Key project information includes:

    Brewing and distilling will operate year-round.

    Brewery will initially include four fermenting tanks. Owner has requested space for at least two additional tanks. Potential expansion will be based on future sales.

    Distillery will produce 16% alcohol, which is classified as a flammable liquid. Fire separations are required.

    Tap Room is designed with seating for 300 people, not including exterior patio seating. It will have views to the working orchards and the historic buildings on site.

    Tap Room is scheduled to be open from August through November. Owner would like options to extend operating dates based on popularity.

    The Market area will feature local farm products and is not conditioned.

    Entire building will be fully sprinklered.

    Selected building materials are low-maintenance, as requested by the Owner, for durability and to reflect the nature of a working farm.

    Mechanical and electrical systems will be hung from the building structure. These loads are included in PEMB shop drawings.

    Public water and sewer is not available at the Project Site.

    Occupancy sensors are included to reduce utility costs and achieve energy conservation requirements.

The following resources are available for your reference:

    Architectural Drawings, including plans, elevations, sections, and schedules

    Consultant Drawings, including structural, HVAC, power distribution, and plumbing

    PEMB Shop Drawings

    Design and Construction Schedule

    Specification Excerpts, showing relevant spec sections

    IBC and ADA Excerpts, showing relevant code and accessibility sections

    After reviewing the documents, the architect discovers a coordination issue in the corridor.

The owner decides to triple the size of the distillery component of the project to make hand sanitizer and wants to use the Tap Room spaces adjacent to the brewery and distillery for this purpose.

Which of the following must the architect reevaluate and change to accommodate this request? Check the three that apply.

Options:

A.

A-01 LIFE SAFETY PLAN


B.

A-02 SITE PLAN


C.

A-03 FLOOR PLAN


D.

A-04 REFLECTED CEILING PLAN


E.

A-05 ROOF PLAN


F.

A-06 EXTERIOR ELEVATIONS


Expert Solution
Questions # 3:

Question # 3

Refer to the exhibit.

An architect is designing a multipurpose room that will operate daycare services as well as exercise classes. The multiple occupancies within the space utilize components of the same means of egress system.

What is the occupant load factor that should be used in calculating egress?

Options:

A.

20


B.

35


C.

50


D.

150


Expert Solution
Questions # 4:

Which of the following documents should be coordinated in the design of a barrier-free building entrance?

Options:

A.

Door schedule, vertical elevations, and structural plans


B.

Hardware schedule, electrical drawings, and sprinkler drawings


C.

Vertical elevations, hardware schedule, and electrical drawings


D.

Door schedule, hardware schedule, and alarm system design


Expert Solution
Questions # 5:

The single-line diagram for the electrical distribution system shown is for a multi-family project.

Click in the box on the single-line diagram where the transformer is located.

Question # 5


Expert Solution
Questions # 6:

Question # 6

Refer to the exhibit.

For a plywood panel carrying the grade stamp shown, which of the following is the maximum recommended span for use in a floor system?

Options:

A.

15 in


B.

16 in


C.

32 in


D.

108 in


Expert Solution
Questions # 7:

Proposed trees along a residential street next to a new development site should first be selected based on which of the following?

Options:

A.

Seasonal foliage, color, and scale


B.

Adaptability to local climate and soil conditions


C.

Dense root systems and wind resistance


D.

Provision of natural habitation for local wildlife


Expert Solution
Questions # 8:

Question # 8

Refer to the exhibit.

During spring rains, the foundation walls around the basement space, as illustrated, experience an increase in lateral pressures.

Which one of the following is also a major concern?

Options:

A.

Moisture absorption of the concrete foundation wall


B.

Increased weight on the footings


C.

Vertical upward pressure on the basement floor


D.

Differential lateral pressure on total building structure


Expert Solution
Questions # 9:

An architect is designing a sub-surface drainage system that outfalls into a site retention pond. The recommended shape, size, and slope of the drainage lines need to be determined for primarily which of the following purposes?

Options:

A.

To minimize the desired flow


B.

To maximize the desired flow


C.

To obtain the desired velocity


D.

To increase the desired velocity


Expert Solution
Questions # 10:

Question # 10

Refer to the exhibit.

Which of the following examples of wood paneling depicts the method of "slip matching" between adjacent wood veneers?

Options:

A.

A


B.

B


C.

C


D.

D


Expert Solution
Viewing page 1 out of 3 pages
Viewing questions 1-10 out of questions