PDD Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

Which of the following documents should be coordinated in the design of a barrier-free building entrance?


A.

Door schedule, vertical elevations, and structural plans


B.

Hardware schedule, electrical drawings, and sprinkler drawings


C.

Vertical elevations, hardware schedule, and electrical drawings


D.

Door schedule, hardware schedule, and alarm system design