Pass the NABCEP NABCEP Board Certifications PVIP Questions and answers with CertsForce

Viewing page 1 out of 5 pages
Viewing questions 1-10 out of questions
Questions # 1:

An 8 AWG bare copper equipment ground conductor (EGC) is wire tied to the module mounting structure of a commercial rooftop solar array. After a few years of operation, some spots on the EGCbegin to turn a green color and appear to be corroding more significantly that other places. What would the MOST likely cause of the problem?

Options:

A.

Nyton wire ties in contact with the copper wire


B.

A break in the EGC, leaving the array ungrounded


C.

Bypass dlode failures inducing current on the EGC


D.

Array racking touching the EGC at multiple points


Expert Solution
Questions # 2:

A PV module has a temperature coefficient of power of -0.4%/°C and a rated power of 300W at STC (25°C). What is the expected power output if the module temperature rises to 55°C?

Options:

A.

264W


B.

276W


C.

288W


D.

300W


Expert Solution
Questions # 3:

A string inverter fails to start in the morning. The DC input voltage is 200V, below the minimum start voltage of 250V. What should be checked first?

Options:

A.

Inverter firmware


B.

String sizing


C.

Module temperature


D.

AC breaker position


Expert Solution
Questions # 4:

The AHJ for enforcement of the NEC has which responsibility?

Options:

A.

Inspecting factory-installed wire and equipment construction methods


B.

Inspecting installations under the exclusive control of the electric utility


C.

Approval equipment installation methods for efficiency, convenience, and adequacy for good service


D.

Making interpretations of the rules and deciding on approval of equipment and material


Expert Solution
Questions # 5:

A residential PV system uses two 120.240Vac utility-interactive inverters with a sealed lead-acid battery energy backup for protected loads. The MOST important protected load consideration when operating in the backup mode is that:

Options:

A.

The protected loads must have automatic restart function.


B.

All protected loads are connected in multiwire branch circuits.


C.

The peak current from the sealed lead- acid batteries must not exceed peak demand currents.


D.

The stand-alone system configuration can adequately supply current to all protected load branch circuit.


Expert Solution
Questions # 6:

A site survey indicates a residential roof with a 4:12 pitch facing 20° east of south. The local latitude is 35°N, and the optimal tilt for maximum annual production is equal to latitude. What adjustment should be made to compensate for the roof’s orientation and tilt to achieve near-optimal output?

Options:

A.

Increase array capacity by 5%


B.

Install adjustable racking to match 35° tilt


C.

Rotate modules 20° west to face true south


D.

No adjustment needed; output loss is negligible


Expert Solution
Questions # 7:

A 7KW/ 14 KWh multimode system has been installed at a residence, ac-couple with the customer’s existing 6.7kwh ac PV system. The system providers uninterrupted power to a protect loads subpanel, which is connected to a refrigerator,

Microwave, 1.0 ton are conditioner, three lightning circuit, and the 6.7kwac PV system. One month later, the homeowner moves additional circuits to the protected loads subpanel, substantially increasing the loads. Why would this cause, the backfed interconnection breaker in the main service panel to trip?

Options:

A.

The main service panel is no longer compliant with NCC 705.12.


B.

The load «the protected loads subpanel exceeds the PV system ac rating by 25%.


C.

The toad exceeds the capacity of the interconnection breaker.


D.

The total load exceeds the system's energy storage capacity of 14kWh.


Expert Solution
Questions # 8:

Which temperature coefficient is used in the calculation to verify energy production of a PV system?

Question # 8

Options:

A.

OptionA


B.

OptionB


C.

OptionC


D.

OptionD


Expert Solution
Questions # 9:

An installer has decided to use 31 in. long. 3.1/2 in diameter conical ground screws as the footings for a 3.840W solar electric system. Access to he is too difficult to pour concrete footings. The soll is classified as sandy loam. The design wind speed is 90 mph with an uplift force of 32 ibs/ft2. What is the MINIMUM number of screw required to resist uplift loads?

Question # 9

Options:

A.

8


B.

10


C.

12


D.

14


Expert Solution
Questions # 10:

A 10 kW array produces 14,000 kWh annually. What is the specific yield in kWh/kW?

Options:

A.

1200


B.

1400


C.

1600


D.

1800


Expert Solution
Viewing page 1 out of 5 pages
Viewing questions 1-10 out of questions