Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

Pass the iSQI iSQI Software testing CTAL-TM_Syll2012 Questions and answers with CertsForce

Viewing page 3 out of 3 pages
Viewing questions 21-30 out of questions
Questions # 21:

Defect Management

Assume you are working on a defect management process to be used by a software organization to track the current status of the defects reports for several projects.

When a defect is found for investigation a defect report is created in “Opened” state that is the unique initial state. The defect report status has also a unique finale state that is the “Closed” state.

The following state transition diagram describes the states of this defect management process:

Question # 21

where only the initial (“Opened”) and final (“Closed”) states are indicated while the remaining states (V, W, X, Y, Z) have yet to be named.

Which of the following assignments would you expect to best complete the defect management process?

Number of correct responses: 1

K32 credits

Options:

A.

V=Rejected , W=Corrected , X=Validated, Y=Re-Opened, Z=Assigned


B.

V=Assigned, W=Validated , X=Corrected, Y=Re-Opened, Z=Rejected


C.

V=Assigned, W=Corrected , X=Validated, Y=Re-Opened, Z=Rejected


D.

V= Corrected, W=Assigned, X=Validated, Y=Corrected, Z=Rejected


Expert Solution
Questions # 22:

Defect Management

During the system testing phase a tester from your test team observes a failure in the system under test and he/she decides to create an incident report. The incident report is currently in a “new” state, indicating it needs to be investigated.

Which THREE of the following information items can’t yet be present in the incident report?

Number of correct responses: 3

K32 credits (2 credits out of 3 credits correct, 1 credit point)

Options:

A.

The type of defect that caused the failure


B.

The actual and the expected result highlighting the failure


C.

The lifecycle phase in which the defect has been introduced


D.

What really caused the failure (actual cause)


E.

Steps to reproduce the failure, including screenshots, database dumps and logs where applicable


Expert Solution
Questions # 23:

Defect Management

Consider a defect report and assume that a part of its lifecycle includes the following states:

New: Is the initial state

Working: Means that the developers are addressing the defect in order to produce a fix for the defect

Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers

Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect

Closed: is the final state

Which of the following answers represents an invalid sequence of states that can’t lead the bug report to the “Closed” state?

Number of correct responses: 1

K21 credit

Options:

A.

New, Working, Verification, Working, Clarification, Working, Verification, Closed


B.

New, Working, Clarification, Working, Verification, Closed


C.

New, Working, Verification, Working, Clarification, Working, Closed


D.

New, Working, Verification, Closed


Expert Solution
Questions # 24:

Test Management

You are performing a quality risk analysis for a CSCI (Computer Software Configuration Item) used to implement a CBIT (Continuous Built-In Test) module of a safety-critical system.

During the quality risk analysis you are trying to identify the ways in which failures of the CBIT module can occur, for each of them trying to determine the potential causes and likely effects, and the risk level (calculated as the product of three factors: severity, occurrence and detection).

Which of the following risk analysis techniques are you working with?

Number of correct responses: 1

K21 credit

Options:

A.

A lightweight product risk analysis technique


B.

Failure Mode and Effect Analysis


C.

Wide Band Delphi


D.

Cost of Exposure


Expert Solution
Questions # 25:

Test Management

Based on the historical data of 5 past and similar projects, you have calculated these average numbers of defects detected in system testing:

- for each 10000 LOC (lines of code), 200 defects

- for each person-month of development team effort, 49 defects

You want to use this information to perform estimation for a new project.

The project manager tells you that he/she has estimated 20000 new LOC for this new project.

Four developers work for four months on this project before system testing.

During system testing, 797 defects are discovered.

Assume that the system test of this new project is using the same amount of work as spent in the past projects.

Based on this information only, which of the following statement is certainly true about this project?

Number of correct responses: 1

K33 credits

Options:

A.

The code for the new project contains a higher defect density than the code of the past projects


B.

The number of defects found during the system test phase on the new project is approximately proportional to the development team effort


C.

40000 LOC have been delivered to system testing (against the 20000 LOC planned by the project manager)


D.

More LOC than planned have been delivered to system testing with a higher defect density than the past projects


Expert Solution
Questions # 26:

You can count on well-written requirements, but you can’t count on an adequate contribution of the stakeholders to the quality risk analysis. You have to mitigate the insufficient contribution of the stakeholders because the risk-based testing approach shall minimize the product risks. Your test team has one expert tester in security testing.

Which of the following test activities would you expect to be the less important in this context?

Number of correct responses: 1

K43 credits

Options:

A.

Extract from the defect tracking system of the previous project all the security defects and failures, and classify them to support design and execution of specific tests


B.

Automate all functional and non-functional system tests


C.

Apply systematic and exploratory testing for integration and system test


D.

Perform exploratory testing sessions with adequate charters covering security aspects


Expert Solution
Questions # 27:

Test Management

The following chart plots the cumulative number of defects opened against the cumulative number of defects closed during system testing of a software product.

Question # 27

Which of the following statements is true?

Number of correct responses: 1

K21 credit

Options:

A.

The chart indicates that you have plenty of problems left to find


B.

The chart can be used to reveal test progress problems


C.

The chart seems to indicate that the defect management process is not working well


D.

The chart seems to indicate that the defect management process is working well


Expert Solution
Questions # 28:

Test Management

Assume you are currently working on a project developing a system where functional requirements are very well specified. Unfortunately non-functional requirements do almost not exist.

You are the Test Manager. You have to choose a technique for test selection that allows testing of non-functional characteristics, especially reliability.

Which of the following techniques for test selection do you expect being most useful in this scenario?

Number of correct responses: 1

K21 credit

Options:

A.

A model-based technique based on the creation of operational profiles


B.

Ambiguity reviews


C.

Test condition analysis


D.

Cause-effect graphing


Expert Solution
Questions # 29:

Your organization is considering using open-source tools. You have been told you need to be aware of the terms of the GNU general public license.

What is the basic concept of this license? [1]

Options:

A.

Anyone can use the software anytime for any reason.


B.

A small license fee must be paid to the supplier of the software.


C.

If you're going to distribute the software, you need to do so with the same terms as were applied when you received the

software.


D.

You are allowed to use the software internally, but it cannot be incorporated into any product for which you will receive a profit.


Expert Solution
Questions # 30:

Your Project Manager has challenged you to come up with a process improvement strategy using the IDEAL model.

Which step within the process defines the success criteria? [2]

Options:

A.

Entrance


B.

Analysis


C.

Diagnosing


D.

Initiation


Expert Solution
Viewing page 3 out of 3 pages
Viewing questions 21-30 out of questions