The Commissioning (Cx) Process has been structured to coincide with the phases of a generic project in which of the following sequences of phases?


A.

OPR, Design, Construction, Operations and Maintenance


B.

Basis of Design (BOD), OPR, Cx, Construction


C.

Pre-Design, Design, Construction, Occupancy and Operations


D.

Basic Design, Construction, Cx, Owner’s Project Requirements (OPR)