The Interior space of a six-story commercial building is being completely renovated. Which of the following actions should the design team conduct first in order to incorporate green building strategies?
A.
Set project goals
B.
Identify improvement opportunities
C.
Benchmark performance of existing building
D.
Measure performance and undergo third party verification
Setting project goals is the action that the design team should conduct first in order to incorporate green building strategies in a six-story commercial building renovation project. Setting project goals is an important step in the integrative process that defines the vision and expectations for the project’s sustainability performance and guides the decision-making throughout the design and construction phases. Setting project goals involves engaging key stakeholders, such as owners, users, designers, contractors, and operators, and identifying measurable objectives, targets, and metrics for various aspects of green building, such as energy efficiency, water conservation, material selection, indoor environmental quality, site selection, and transportation access. The LEED Green Associate Candidate Handbook states that one of the steps in the integrative process is to “establish sustainability goals early in project development” [1, p. 12]. References: LEED Green Associate Candidate Handbook, [Integrative Process | U.S. Green Building Council]
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit