Cycle Time is a lagging indicator, meaning it can only be measured after a work item is complete. Therefore, it cannot be used as a leading indicator of the length of the feedback loop (Option A). Additionally, Cycle Time is not typically used during the Daily Scrum to help Developers inspect and adapt their Sprint; rather, it is more often used to assess overall process efficiency