Question #: 12
Topic #: 2

The Cycle Time metric for a certain Work Item cannot be used:

(choose the best two answers)


A.

As a leading indicator to the length of the feedback loop for that Work Item.


B.

To help the Scrum Team inspect and adapt their process.


C.

As a lagging indicator to the length of the feedback loop for that Work Item.


D.

To help the Developers inspect and adapt their Sprint in the Daily Scrum.


E.

To influence the team's SLE.