Scrum Professional Scrum with Kanban (PSK 1) Exam PSK-I Question # 13 Topic 2 Discussion

Scrum Professional Scrum with Kanban (PSK 1) Exam PSK-I Question # 13 Topic 2 Discussion

PSK-I Exam Topic 2 Question 13 Discussion:
Question #: 13
Topic #: 2

What is true about the Sprint Goal if the Developers reserve capacity for unplanned work during

an upcoming sprint?

(choose the best answer)


A.

The Sprint Goal no longer helps the Developers. They do not know what they will be

working on.


B.

The Developers should never reserve more than 5% capacity for unplanned work. It

is inefficient if the Developer's forecast does not take into account all of their

capacity.


C.

The Sprint Goal becomes more important. It can help the Developers maintain their

focus as new Product Backlog items are brought into the Sprint Backlog.