When using Kanban in a Scrum environment, some resistance toward introducing Work in Progress (WIP) Limits may be encountered. What is an alternative to introducing WIP Limits in Kanban?


A.

Using Kanban boards that improve visualization and enhance communication.


B.

None, Professional Scrum with Kanban cannot be used without explicit WIP Limits.


C.

Building a strong team identity using Squads and tribes.


D.

Conducting Daily Stand-Up meetings that control not having too much work.