PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 98 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 98 Topic 10 Discussion

PMI-002 Exam Topic 10 Question 98 Discussion:
Question #: 98
Topic #: 10

A Project with a total funding of $70,000 was finished with a BAC value of $60,000. What term can best describe the difference of $10,000?


A.

Cost Variance


B.

Management Overhead


C.

Management Contingency Reserve


D.

Schedule Variance


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.