New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 99 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 99 Topic 10 Discussion

PMI-002 Exam Topic 10 Question 99 Discussion:
Question #: 99
Topic #: 10

You are the Project Managers of ABC company. The Project team members are from the finance and accounts. The team members report to Finance and Account Managers respectively, and you have limited control over them. What type of organizational hierarchy does ABC company follow?


A.

Matrix organization


B.

Projectized organization


C.

Functional organization


D.

None


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.