Question #: 99
Topic #: 10

You are the Project Managers of ABC company. The Project team members are from the finance and accounts. The team members report to Finance and Account Managers respectively, and you have limited control over them. What type of organizational hierarchy does ABC company follow?


A.

Matrix organization


B.

Projectized organization


C.

Functional organization


D.

None