PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 97 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 97 Topic 10 Discussion

PMI-002 Exam Topic 10 Question 97 Discussion:
Question #: 97
Topic #: 10

In crashing a schedule, you would focus on:


A.

Accelerating as many tasks as possible


B.

Accelerating just the non-critical tasks


C.

Accelerating the performance of tasks on the critical path


D.

None of the above


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.