PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 96 Topic 10 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 96 Topic 10 Discussion

PMI-002 Exam Topic 10 Question 96 Discussion:
Question #: 96
Topic #: 10

What is the difference between a Verify Scope process and quality control?


A.

There is no difference.


B.

Verify Scope is primarily concerned with the correctness of work results while quality control is primarily concerned with the acceptance of work results.


C.

Verify Scope is concerned with ensuring that changes are beneficial while quality control is concerned that the overall work results are correct.


D.

Verify Scope is primarily concerned with the acceptance of work results while quality control is primarily concerned with the correctness of work results.


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.