Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 6 Topic 1 Discussion

PMI Certified Associate in Project Management (CAPM) Certification PMI-002 Question # 6 Topic 1 Discussion

PMI-002 Exam Topic 1 Question 6 Discussion:
Question #: 6
Topic #: 1

___________ is a group of processes required to purchase or acquire the products, services, or results needed from outside the project team to perform the work.


A.

Procurement Management


B.

Planning Management


C.

Scope Management


D.

Control Management


Get Premium PMI-002 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.