Question #: 5
Topic #: 1

You are managing a project that will implement a new Insurance software package. Two project team members have difficulty working together. They come to you, for help resolving the issues. You immediately set up a meeting that includes the functional manager. After the meeting you and the functional manager discuss the issues and agree on a solution. What type of organizational structure you are working in?


A.

Functional


B.

Balanced matrix


C.

Piojectized


D.

Strong Matrix