Isaca Certified in Risk and Information Systems Control CRISC Question # 1 Topic 1 Discussion

Isaca Certified in Risk and Information Systems Control CRISC Question # 1 Topic 1 Discussion

CRISC Exam Topic 1 Question 1 Discussion:
Question #: 1
Topic #: 1

What should be the PRIMARY objective for a risk practitioner performing a post-implementation review of an IT risk mitigation project?


A.

Documenting project lessons learned


B.

Validating the risk mitigation project has been completed


C.

Confirming that the project budget was not exceeded


D.

Verifying that the risk level has been lowered


Get Premium CRISC Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.