Question #: 86
Topic #: 9
A vendor ' s planned maintenance schedule will cause a critical application to temporarily lose failover capabilities. Of the following, who should approve this proposed schedule?
The business application owner is responsible for the operation and risk decisions related to the application. Since the loss of failover may impact business continuity, their approval is essential.