Question #: 2
Topic #: 1

For no apparent reason, the time required to complete daily processing for a legacy application is approaching a risk threshold. Which of the following activities should be performed FIRST?


A.

Temporarily increase the risk threshold.


B.

Suspend processing to investigate the problem.


C.

Initiate a feasibility study for a new application.


D.

Conduct a root-cause analysis.