COBIT-2019 Exam Topic 1 Question 5 Discussion:
Question #: 5
Topic #: 1

Who is responsible for performing a stakeholder satisfaction survey and gathering feedback on lessons learned from the implementation of an EGIT program plan?


A.

The CIO and the program steering committee


B.

Business executives and the l&I governance board


C.

IT managers and IT process owners


D.

The risk and compliance function and IT audit