Who is responsible for performing a stakeholder satisfaction survey and gathering feedback on lessons learned from the implementation of an EGIT program plan?
The CIO and the program steering committee are responsible for performing a stakeholder satisfaction survey and gathering feedback on lessons learned from the implementation of an EGIT program plan. According to the COBIT 2019 Implementation Guide, the CIO is the executive sponsor of the EGIT program, who provides strategic direction, leadership, and oversight for the program. The program steering committee is a group of senior stakeholders who support the CIO in governing and monitoring the program. One of their responsibilities is to conduct regular reviews of the program performance and outcomes, including stakeholder satisfaction and lessons learned. These reviews help to evaluate the effectiveness and efficiency of the EGIT program plan and identify areas for improvement. References: : COBIT 2019 Implementation Guide: Implementing and Optimizing an Information and Technology Governance Solution, page 23 1 : COBIT 2019 Implementation Guide: Implementing and Optimizing an Information and Technology Governance Solution, page 45 1
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit