BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 145 Topic 15 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 145 Topic 15 Discussion

ISEB-PM1 Exam Topic 15 Question 145 Discussion:
Question #: 145
Topic #: 15

What is the first step in preparing the risk register?


A.

Qualitative risk analysis


B.

Quantitative risk analysis


C.

Risk response planning


D.

Risk identification