What type of project structure is a hierarchically organized depiction of the resources by type?


A.

Organizational Breakdown Structure (OBS)


B.

Resource Breakdown Structure (RBS)


C.

Work Breakdown Structure (WBS)


D.

Project Breakdown Structure (PBS)