BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 143 Topic 15 Discussion

BCS Foundation Certificate in IS Project Management ISEB-PM1 Question # 143 Topic 15 Discussion

ISEB-PM1 Exam Topic 15 Question 143 Discussion:
Question #: 143
Topic #: 15

Project team members begin to address the project work and technical decisions. The project team is in which of the following stages of team development?


A.

Storming


B.

Forming


C.

Norming


D.

Performing