Question #: 146
Topic #: 15

Continually measuring and monitoring the actual cost versus the budget is done to _____.


A.

None of the other alternatives apply


B.

analyze the reasons for variances


C.

establish the variances


D.

identify the problems


E.

All of the other alternatives apply.