Which party is usually required to maintain record drawings during the project according to the Project Delivery Practice Guide?
Architect
Contractor
Owner
Authority having jurisdiction
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
According to CSI’s Project Delivery Practice Guide and CDT body of knowledge, the Contractor is typically required—by the conditions of the Contract—to maintain record drawings during construction. These are sometimes called “as-built” or “marked-up” drawings.
CSI explains that:
The Contractor must keep on site a current set of drawings and, as the work progresses, mark changes, deviations, and concealed conditions that differ from the original contract drawings.
This responsibility is usually stated in the General Conditions and/or Division 01, and is part of the contractor’s obligation to provide Project Record Documents at closeout.
At the end of the project, these contractor-maintained record drawings and related record information are typically delivered to the Architect/Engineer and then to the Owner as part of closeout, but the party maintaining them during the project itself is the Contractor.
The Architect uses the contractor’s record information to prepare formal record documents only if required by the contract, but the day-to-day updating and maintenance during construction is assigned to the Contractor in standard CSI-aligned practice.
Relevant CSI concepts (paraphrased):
CSI Project Delivery Practice Guide – sections on “Construction Phase” and “Project Record Documents” explaining that the contractor keeps a set of marked-up record drawings during the work.
CSI CDT Study Materials – topic on roles and responsibilities for record documents and closeout.
Which team member is actively involved and interested in all phases of the project?
Contractors
Owners
Architects/engineers
Manufacturers/suppliers
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI’s project delivery framework places the owner at the center of the facility life cycle. The owner:
Initiates the project by defining needs and project goals.
Selects the project delivery method and engages the design and construction teams.
Participates in planning, design decisions, funding, and approvals.
During construction, the owner is responsible for payments, change decisions, and acceptance of the work.
After construction and closeout, the owner (often through a facility management group) is responsible for operation, maintenance, and long-term performance of the facility.
CSI repeatedly highlights that only the owner is engaged from the earliest concept through long-term operation and eventual renovation or disposal. All other parties (designers, contractors, manufacturers) participate for limited phases.
Therefore, the party “actively involved and interested in all phases of the project” is clearly:
B. Owners
Why the other options are incorrect:
A. ContractorsContractors typically become formally involved at procurement/bidding and remain through construction and closeout. They usually have no role in early planning (except in some delivery methods like CM-at-Risk or IPD where they join during design) and no long-term responsibility for operations beyond warranty obligations.
C. Architects/engineersThe A/E’s primary involvement is during planning and design, and then construction administration during construction and closeout. After the project is turned over, their involvement often ends unless separately engaged for post-occupancy evaluations or future work. They do not normally manage day-to-day operations and maintenance.
D. Manufacturers/suppliersManufacturers and suppliers participate mainly in product selection, submittals, and furnishing materials and equipment during design-assist and construction phases. They may have continuing obligations for warranties or support, but they are not engaged in every phase of the project’s life cycle as the owner is.
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – roles and responsibilities of the owner, design professional, contractor, and others.
CSI Facility Management Practice Guide – owner’s role during operations and the extended facility life cycle.
CSI CDT Study Materials – diagrams and explanations of project participants over the facility life cycle.
Where are the limits of the work of each alternate defined?
Agreement
Bid Form
Division 01
Sections in Divisions 02–49
Comprehensive and Detailed Explanation (CSI-aligned, paraphrased)
In CSI’s organization of the Project Manual:
Division 01 – General Requirements coordinates administrative and procedural requirements that apply across the technical sections.
One of the standard Division 01 topics is “Alternates”.
In CSI practice:
The Bid Form provides the spaces for bidders to state the prices for each alternate.
The Agreement may list accepted alternates after award.
The technical sections (Divisions 02–49) describe detailed materials and methods, but do not typically define the overall limits or scope of each alternate in one place.
Instead, CSI recommends that the description of each alternate, including its limits and what parts of the Work are added, deleted, or changed, be clearly defined in Division 01 – General Requirements, usually in a section titled “Alternates”. There, the scope of each alternate is described in a way that can be coordinated with and referenced by the technical sections.
Therefore, the correct answer is:
C. Division 01
Why the other options are not best per CSI practice:
A. Agreement – The Agreement (Contract for Construction) may list which alternates are accepted once the contract is formed, but it does not typically define in detail the limits of each alternate; it relies on the specifications for those definitions.
B. Bid Form – The Bid Form is where prices for alternates are entered. It may briefly name or reference each alternate, but the detailed definition and limits are in Division 01.
D. Sections in Divisions 02–49 – Technical sections contain the work results and may note how an alternate affects them (e.g., “this finish is used only if Alternate 2 is accepted”), but the primary, consolidated description of what each alternate includes/excludes is in the Division 01 Alternates section.
Key CSI-Related Reference Titles (no links):
CSI Construction Specifications Practice Guide – Division 01 General Requirements and Alternates.
CSI Project Delivery Practice Guide – procurement and alternates sections.
CSI CDT Study Materials – organization of the Project Manual and the role of Division 01.
What could a reference standard specification be based upon?
Project manual for similar project
Design intent
Trade association standard
Manufacturer's specification section
CSI identifies several types of specifications, including:
Descriptive specifications – describe materials and methods in detail.
Performance specifications – describe required results and performance criteria.
Proprietary specifications – designate specific products or manufacturers.
Reference standard specifications – define requirements by citing recognized industry standards rather than repeating all technical details.
A reference standard specification works by referring to standards issued by organizations such as:
Trade associations (e.g., industry associations),
Standards organizations (e.g., ASTM, ANSI, ISO),
Other recognized bodies that publish consensus technical standards.
The specification then simply states that materials, products, or work must comply with the named standard. This reduces repetition and promotes consistency and clarity.
Therefore, a proper basis for a reference standard specification is a trade association standard, which is Option C.
Why the other options are incorrect:
A. Project manual for similar projectPrevious project manuals may be informal references for the specifier, but they are not recognized standards. A reference standard specification must refer to a published technical standard, not another project’s contract documents.
B. Design intentDesign intent is expressed more directly in performance or descriptive specifications, not in reference standard form. Reference standards rely on external, recognized standards, not internal design intent statements alone.
D. Manufacturer's specification sectionReferring to a specific manufacturer’s literature or section is characteristic of a proprietary specification, not a reference standard specification. Reference standards must be based on independent, consensus-based standards, not one manufacturer’s materials.
Key CSI Reference Titles (no links):
CSI Construction Specifications Practice Guide – Types of specifications, including reference standard specifications and their proper use.
CSI Project Delivery Practice Guide – Relationship of specifications to industry standards.
CDT Body of Knowledge – “Specification Types and Methods of Specifying.”
When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?
The architect/engineer/owner team can consider bid listing and bid depository provisions.
Require bidders to provide a list of their intended subcontractors along with their bid.
The subcontractor can withhold their prices from the bidder until the final moments before the deadline.
The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.
Within the CSI / CDT framework, bid shopping is the practice of a prime bidder (typically a general contractor) using one subcontractor’s price to pressure that subcontractor or competitors into lowering their price after bids have been received. CSI treats this as an unethical and undesirable practice that increases risk and undermines fair competition in the procurement process.
Practices that help minimize bid shopping include:
Bid listing and bid depository provisions (Option A):Some public agencies require that the general contractor list major subcontractors with the bid or use a bid depository system. These mechanisms are intended specifically to discourage bid shopping by locking in the subcontractors named at bid time and making the process more transparent.
Requiring bidders to provide a list of intended subcontractors with their bid (Option B):This is another form of sub-bid listing. By compelling the prime bidder to identify subcontractors at bid submission, it restricts their ability to shop sub-bids afterward, thereby minimizing the risk of bid shopping.
Subcontractors withholding their prices until close to bid time (Option C):While not ideal from a coordination standpoint, this is a common subcontractor strategy in a competitive environment to reduce the time window during which a prime contractor can use their number to shop for a lower price. This can mitigate bid shopping risk from the subcontractor’s perspective.
By contrast:
D. The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.This is essentially a description of bid shopping behavior. Asking a subcontractor to “re-evaluate” to get a lower price after their number has been used to compile the bid (especially when using other subs’ prices as leverage) is exactly what public procurement provisions try to prevent. This does not minimize the risk of bid shopping; it is bid shopping.
Therefore, the only option that clearly does not reduce or prevent bid shopping is D.
Relevant CSI-aligned references (no URLs):
CSI Project Delivery Practice Guide – Procurement and Bidding chapters (discussion of competitive bidding ethics and bid shopping).
CSI CDT Body of Knowledge – Procurement and bidding procedures and ethical practices in public work.
During which stage of a facility's life cycle are operations and maintenance documents presented to the owner?
After the authorities having jurisdiction issues a permit
Closeout phase
Preconstruction phase
Construction phase
Comprehensive and Detailed Explanation From Exact Extract (CSI-aligned, paraphrased)
CSI organizes the facility life cycle into phases such as planning, design, construction, closeout, and operations/occupancy. Within this framework, CSI describes project closeout as the phase where the contractor and design team complete all remaining contractual obligations and formally turn the project over to the owner.
A key part of that turnover is providing the owner with operations and maintenance (O&M) information, often including:
Operating and maintenance manuals for equipment and systems
Warranties and guarantees
Spare parts lists and recommended maintenance procedures
As-built/record documentation and, sometimes, commissioning records and training materials
CSI indicates that these O&M documents are to be delivered as part of the closeout requirements, usually at or near Substantial Completion or Final Completion, so that the owner can properly operate and maintain the facility during the occupancy phase.
Therefore the correct answer is B. Closeout phase.
Why the other options are incorrect:
A. After the authorities having jurisdiction issues a permitPermits are typically issued during design or preconstruction, authorizing the start of work. At this time, the facility is not built and O&M documentation does not yet exist in final form. CSI treats permits as part of regulatory approvals, not the turnover of maintenance information.
C. Preconstruction phasePreconstruction focuses on activities like finalizing construction documents, bidding, procurement planning, and initial mobilization. O&M manuals cannot be finalized because products and systems are not yet fully installed, tested, and accepted.
D. Construction phaseDuring construction, some O&M information may be started or submitted in draft form, but CSI’s guidance is clear that formal delivery of complete O&M documentation is a closeout requirement, not an in-progress construction requirement.
Key CSI-Related References (titles only):
CSI Project Delivery Practice Guide – facility life cycle and project closeout chapters.
CSI Construction Specifications Practice Guide – Division 01 sections (Closeout Submittals, Operation and Maintenance Data).
CSI CDT Study Materials – topics on project closeout, warranties, and O&M documentation.
Which document obligates the architect/engineer to review submittals during construction administration?
AIA Document A201, General Conditions of the Contract for Construction
AIA Document B101, Standard Form of Agreement Between Owner and Architect
AIA Document D200, Project Checklist
AIA Document G612, Owners Instructions to the Architect
In CSI/CDT study materials, a key concept is that each party’s legal obligations come from their own agreement:
The owner–contractor relationship is defined in the Owner–Contractor Agreement and its General Conditions (commonly AIA A201).
The owner–architect relationship is defined in the Owner–Architect Agreement (commonly AIA B101).
The architect’s duty to provide construction administration services, including reviewing submittals, is a service owed to the owner and is therefore set out in the Owner–Architect Agreement, not the General Conditions.
In AIA’s standard structure (which CSI uses extensively in CDT):
AIA B101 (Owner–Architect Agreement) lists the architect’s basic services, including:
Construction Phase Services
Review of submittals (shop drawings, product data, samples, etc.)This is what legally obligates the architect to review submittals as part of their contracted services to the owner.
AIA A201 (General Conditions) describes the architect’s role in the context of the construction contract between owner and contractor (e.g., the architect will review submittals in accordance with the Contract Documents), but the architect’s obligation itself arises from B101, which is the contract between owner and architect.
Therefore, the document that actually obligates the architect/engineer (A/E) to perform submittal review as part of construction administration is AIA Document B101 → Option B.
Why the other options are incorrect:
A. AIA Document A201, General Conditions of the Contract for ConstructionA201 is part of the Owner–Contractor contract. It establishes procedures and the architect’s function with respect to the contractor, but it does not itself create the architect’s contractual obligation to the owner; that comes from B101. A201 can describe what the architect will do “as provided in the Owner–Architect Agreement,” but the promise from the architect is in B101.
C. AIA Document D200, Project ChecklistD200 is a non-contractual guide/checklist used for planning and scoping services. It is an aid, not a contract, and does not bind the architect to perform submittal review.
D. AIA Document G612, Owners Instructions to the ArchitectG612 is also a form tool, used for gathering owner’s instructions and information; it is not itself the agreement that defines the architect’s scope of services and obligations.
CSI / CDT-aligned references (no links):
CSI Project Delivery Practice Guide – discussions of standard AIA documents and how responsibilities are allocated between owner, architect, and contractor.
CSI Construction Specifications Practice Guide – sections on relationships between A201 and B101.
CDT Exam references to AIA A201 – General Conditions and AIA B101 – Owner–Architect Agreement in the “Agreements & Conditions of the Contract” domain.
To avoid miscommunication problems during construction, which best practice should the design professional use?
Develop a good working relationship for verbally addressing problems as they arise
Mark emails and electronic communications as "Urgent!" to ensure they are read right away
Distribute meeting minutes to all attendees and concerned parties documenting key decisions and action items resulting from the meeting
Leave detailed voicemail messages describing everything that needs to be done so there is a record of the direction
CSI and CDT principles stress that clear, timely, and documented communication is essential to avoid disputes and miscommunication during construction. Among the key tools for this are:
Written records of decisions, instructions, and clarifications
Formal meeting minutes that are distributed and retained as part of the project record
Consistent use of designated channels (e.g., RFIs, submittals, change documents)
In construction phase administration, progress meetings and other coordination meetings are routinely held. Best practice, as described in CSI guides and standard contract documents, is that:
One party (often the architect or construction manager) prepares written meeting minutes.
These minutes record attendance, topics discussed, decisions made, and action items (with responsible parties and due dates).
The minutes are then distributed to all attendees and other concerned parties, providing a shared, written understanding and an opportunity to correct any errors.
This practice directly addresses the question’s goal: avoiding miscommunication problems during construction. Therefore, the best answer is Option C.
Why the other options are weaker:
A. Develop a good working relationship for verbally addressing problems as they ariseA good working relationship is very important, but verbal-only communication is risky. CSI emphasizes that important decisions and directions must be documented in writing.
B. Mark emails and electronic communications as "Urgent!"This may get attention but does not ensure clarity, completeness, or shared understanding, and overuse can even reduce effectiveness.
D. Leave detailed voicemail messagesVoicemail is not a reliable or easily referenced project record. It is difficult to circulate, file, search, or confirm, and can easily be misunderstood or lost. CSI emphasizes written, project-file communication over voicemail.
Relevant CSI / CDT References (titles only, no links):
CSI Project Delivery Practice Guide – chapters on “Construction Phase” and communication and documentation.
CSI Construction Specifications Practice Guide – Division 01 sections on “Project Management and Coordination” and “Project Meetings,” including requirements for meeting minutes.
CDT Body of Knowledge – communication and documentation practices in construction administration.
Within the context of the construction industry, what does BIM stand for?
Building Information Modeling
Business Information Manual
Building Interior Maintenance
Building Inspection Manual
Comprehensive and Detailed Explanation From Exact Extract (CSI-based)
In CSI’s project delivery and documentation discussions, BIM is consistently defined as “Building Information Modeling.”
CSI describes BIM as:
A digital representation of the physical and functional characteristics of a facility.
A shared knowledge resource for information about a facility, forming a reliable basis for decisions during its life cycle.
A tool that supports coordination, clash detection, documentation, quantity takeoff, and communication between design and construction team members.
BIM models are used alongside, and coordinated with, drawings, specifications, and other contract documents, and they support communication and decision-making throughout design, construction, and sometimes operation.
The other options are not recognized industry meanings of BIM:
B. Business Information Manual – not a standard construction-industry term.
C. Building Interior Maintenance – does not match CSI or industry definitions of BIM.
D. Building Inspection Manual – again, not the accepted meaning of BIM in the AEC context.
Therefore, in the construction context, BIM stands for “Building Information Modeling” (Option A).
Key CSI References (titles only):
CSI Project Delivery Practice Guide – chapters addressing BIM and information management.
CSI Construction Specifications Practice Guide – discussions of model-based delivery and coordination with specifications.
CSI CDT Body of Knowledge – terminology and emerging practices including BIM.
Which term or word is appropriate to use in specification text?
Any
As per
As required
Work
CSI’s Construction Specifications Practice Guide and CDT materials provide clear guidance on appropriate wording in specifications. They stress:
Use clear, specific, and enforceable language.
Avoid vague, subjective, or nontechnical terms that create ambiguity and open interpretation.
Among the answer choices, “Work” is the only word that is appropriate and standard in CSI-compliant specification text:
“Work” is a defined term in the General Conditions (and often Division 01), usually meaning the total construction and services required by the Contract Documents, including all labor, materials, equipment, and services necessary to complete the project.
Because it is defined and used consistently, “Work” is an acceptable and precise term for specification language. Example usage (conceptually): “Perform all Work in accordance with…”.
Why the other terms are inappropriate per CSI guidance:
A. AnyCSI recommends avoiding “any,” “either,” “etc.” and similar words because they are non-specific and create ambiguity. For example, “provide any fasteners as needed” does not clearly define what is required and can lead to disputes and inconsistent interpretation.
B. As perThe phrase “as per” is discouraged in CSI-style writing. It is considered informal and can be replaced by clearer, more direct phrasing such as “in accordance with,” “according to,” or “as indicated in.” CSI advocates for concise, plain, and unambiguous English in specs.
C. As requiredCSI strongly cautions against phrases like “as required” or “as necessary” when they are not tied to a clear condition or reference. They shift the decision to someone’s judgment later, instead of stating the requirement explicitly. If something is required, the specification should state what, when, and under what conditions, rather than simply saying “as required.”
Therefore, in a CSI-compliant specification, the term that is clearly appropriate from the options given is “Work” (Option D).
Relevant CSI references (no URLs):
CSI Construction Specifications Practice Guide – Chapters on language and writing style for specifications (clear, concise, complete, correct).
CSI Practice Guide for Principles & Formats of Specifications – Guidance on defined terms such as “Work.”
CSI CDT Body of Knowledge – Sections on specification-writing best practices and prohibited vague phrases.