CDT Exam Topic 3 Question 25 Discussion:
Question #: 25
Topic #: 3

When a public works project utilizes design-bid-build, which option would NOT minimize the risk of bid shopping?


A.

The architect/engineer/owner team can consider bid listing and bid depository provisions.


B.

Require bidders to provide a list of their intended subcontractors along with their bid.


C.

The subcontractor can withhold their prices from the bidder until the final moments before the deadline.


D.

The bidder can ask the subcontractor to reevaluate their prices to find a lower price after the subcontractor has submitted their price.